project details

Southeast WPCP - Medium Voltage
CLIENT:  San Francisco Public Utilities Commission (SFPUC) (415.551.4603)

Location:
San Francisco, Ca
Contract #:
WW-514R
Start Date:
January 2011
Completion Date:
March 2012
Total Contract Amount:
$2,179,174