Harry Tracy WTP/Filter Upgrade
CLIENT:  Eric Gee (SFPUC) (925.862.5761)

Location:
San Bruno, CA
Contract #:
WD-2478
Start Date:
September 2005
Completion Date:
February 2006
Total Contract Amount:
$1,641,595

The work on this project consisted of a prechlorination full scale demonstration filters upgrade, retrofit filters, remove and replace filter media, construct plastic block and monoflor underdrain system, construction of polymer pumps and mechanical piping, instrumentation, construct fiberglass troughs. The project is located in San Bruno, CA.